TxDOT Is Closing the 2222-to-Southbound-360 Ramp. Here's What Changes at the Junction Through 2029

Heading east on RM 2222 toward Loop 360, the old move was simple. You took the entrance ramp onto southbound 360 and merged. TxDOT's new traffic pattern closes that ramp. Southbound traffic goes to the RM 2222 signal instead, where you turn right to reach southbound Loop 360. The map TxDOT posted for the change is dated August 31, 2026.

If you live in Northwest Hills, this interchange is your front door to the west side of Austin, and the new pattern can feel like a short fall detour. It's really the opening of a four-phase rebuild. The piece that changes the RM 2222 junction for good is phase three, and TxDOT doesn't expect the whole project to finish until late 2029.

What's changing at the 2222 ramps this fall

The TxDOT Courtyard Drive/RM 2222 project page lists two new traffic patterns at RM 2222:

  • Eastbound RM 2222 to southbound Loop 360: the entrance ramp will close. Drivers turn right at the RM 2222 signal to get onto southbound 360.
  • Northbound Loop 360 exit to RM 2222: the exit lanes change to left turn only, left turn/straight, and right turn only.

Those two changes matter most on the drive home from the south. Under the new pattern, coming up 360 from Westlake or downtown means picking your lane at the exit ramp by where you're headed on 2222, before you reach the signal.

TxDOT hasn't published an end date for this arrangement. Overnight closures come and go on top of it. In mid-October the agency listed rolling closures on westbound RM 2222 between Loop 360 and City Park Road, plus a night when the westbound 2222 entrance ramp to northbound 360 was shut. Those specific nights have passed. The project page is the place to check before a late drive. Daytime work runs weekdays from 7 a.m. to 7 p.m., with Saturday work from 7 a.m. to 3 p.m. as needed.

Why the junction you use is built third

The project covers nearly a mile of Loop 360, from Courtyard Drive to RM 2222, as KXAN described it. TxDOT has split it into four phases, in this order:

  1. Set up the work zone, build waterlines and excavate cliffs.
  2. Build new northbound and southbound connector roads, drainage, braided ramps and the Courtyard Drive bridge, and start the shared-use paths.
  3. Build the RM 2222 diverging diamond interchange and finish the shared-use paths.
  4. Do final paving and striping, then open the permanent traffic patterns.

That sequence is strict. The Austin American-Statesman's construction guide, published May 18, 2026, reported that the Courtyard bridge will be finished before phase three work starts at RM 2222. The same guide said TxDOT didn't yet have contractor dates for when each phase would begin.

We do have a few markers. The KXAN report said phase one, the waterline and cliff work, was expected to continue until summer 2027. In May, a TxDOT spokesperson told the Austin Chronicle that phase two was tentatively about a year away, with the timeline subject to change. Phase two is when drivers lose the ability to cross Loop 360 at Courtyard Drive and get rerouted along 360, according to the Statesman. Work will start on the east side, next to the northbound lanes, and move west.

Put those together and the order is clear. First the cliffs, then Courtyard, and only after that the interchange at RM 2222. The temporary patterns at 2222 are the setup for a project whose main work is still a phase or two away.

The finish line has already moved once

The project broke ground in April 2026. Webber is the contractor, and TxDOT's construction sheet estimates three to four years of work. The Statesman's highway project tracker shows how far the numbers have moved:

Earlier figure

Current figure

Projected completion

2028

Late 2029

Budget

$42 million

$68.4 million

The money comes from TxDOT and the City of Austin's 2016 Mobility Bond, according to TxDOT's construction sheet. The Chronicle reported Federal Highway Administration funding as well, and said the federal money is formally obligated to the project.

The cliffs are part of why phase one is heavy work. In early May 2024, rocks fell from the limestone cliffs near the Pennybacker Bridge late at night, and Loop 360 stayed closed until shortly after 2 a.m., KXAN reported. TxDOT's West Cliffs fact sheet says the rockslide damaged cliffs on the west side of Loop 360, and the plan calls for excavating and removing 155,000 cubic yards of material. The Statesman tracker notes that no changes are planned for the Pennybacker Bridge itself.

What the diverging diamond does once it's built

A diverging diamond interchange briefly moves traffic to the left side of the road. TxDOT's DDI fact sheet describes it in three moves:

  • Left turns: signals at the crossover points shift you to the left, so you can turn left without waiting for oncoming traffic to clear.
  • Straight through: you cross over, continue, then shift back to the right.
  • Right turns: where there's room, a bypass lane handles them.

The Statesman tracker notes this design is often used where there's a lot of left-turning traffic. The nearest local comparison is the RM 1431 and I-35 interchange in Round Rock. TxDOT's results sheet for that DDI compares 2012 with 2016. Traffic volume rose 45% over those four years, yet travel times dropped 13% in the morning in both directions, and 58% eastbound and 44% westbound in the afternoon. Those figures come from a different interchange with different traffic, so they show what the design has done elsewhere, not what it will do at RM 2222.

TxDOT has also explained who the signal removals are meant to help. Speaking to the Austin Chronicle, a TxDOT public information officer said about 90% of the corridor's traffic is passing through. In her view, taking out signals helps local drivers most, because they're the ones who sit waiting for that volume to clear. "The goal is to improve mobility for drivers, but we're also improving options for pedestrians and cyclists, too," she told the paper.

Two changes you'll feel before the interchange opens

The first is the Pennybacker Bridge overlook. For years people reached it by parking on the Loop 360 shoulders, and the new road design eliminates those shoulders. The Chronicle reported that this parking was always illegal, though often not enforced, and that Austin City Council voted unanimously in December 2024 to buy about 1.5 acres near West Courtyard Drive and Loop 360 for replacement parking, sidewalks and trails. If the overlook is where you take visiting family, plan on that access changing as the work moves along.

The second is the work itself. KXAN reported that crews often work six days a week, from 7 a.m. to 7 p.m., and neighbors next to the work zone told the station about the noise. TxDOT's project page warns of more noise, vibration and dust during excavation and night work. When the project wraps up, TxDOT says the corridor will have sidewalks and shared-use paths within the project limits.

The next project starts at Spicewood Springs

Courtyard/RM 2222 is one of five projects in TxDOT's Loop 360 program. The next one closer to Northwest Hills is Lakewood Drive/Spicewood Springs Road. It removes the Loop 360 mainlane signals at Lakewood Drive, at Spicewood Springs Road East/Bluffstone Drive, and at Spicewood Springs Road West. At Lakewood and at Spicewood East/Bluffstone, the mainlanes will go over the cross street. That project was environmentally cleared in summer 2023. Utilities get relocated first, and construction depends on funding, with the earliest possible start in 2029.

That means work at Spicewood Springs could begin the same year the RM 2222 interchange is due to finish.

If you're planning a sale or purchase around the Loop 360 work, construction phases and access changes can affect showing routes, commute estimates and timing. We follow these schedules closely for our Northwest Hills clients. Albert Allen can walk you through what the current phase means for your plans. Schedule a discovery call and get private access to Austin listings.

Looking to Sell?

What is your Northwest Hills home worth?

I'll prepare a complimentary home valuation based on recent nearby sales and the details buyers pay for in your area: lot, layout, updates and condition.

Get Your Home Valuation

Discover the Difference

We are committed to guiding you every step of the way, whether you're buying a home, selling a property, or securing a mortgage. Whatever your needs, we've got you covered.

Sign-Up for Off-Market Listings.

Get exclusive access to off-market listings before they hit the public market.

Curious about your home's Value

Curious about your home's value? Get a free, no-obligation home valuation today.

Follow Me on Instagram